The technical evaluation of bids submitted for the project connecting Crete to the mainland grid through direct-current cables was completed, the Independent Power Transmission Operator (ADMIE) said on Thursday, according to ANA.
The following companies made it to the next stage, listed consecutively by section (four sections in total):
– The study, supply and installation of one of two submarine cables between Crete and Attica, and the electrode stations on both locations: Prysmian and Nexans. This section is budgeted at 255 million euros.
– The section related to laying the second submarine cable: Prysmian and Nexans. Budget: 225 million euros.
– The subterranean sections of cables connecting the transformer stations on Crete and Attica to the submarine cables: Prysmian, Nexans and NKT-Hellenic Cables. Budget: 115 million euros.
– The study, supply and installation of optical fiber cables: Prysmian. Bugdet: 20 million euros.