The new Corinth-Patras motorway will be delivered in March 2017. The total toll cost from Corinth to Patras will be 11,5 euros instead of 6,40 that is today.
After the completion of the motorway, the distance between Athens and Patras will be 201,5 km.
The project includes 29 interchanges, 29 tunnels of 25.6km, 80 bridges, 242 footbridges and rest areas.
The total cost of the project reached 2 billion euros.
The works will continue after March in four difficult points at Derveni, Arahovitika and Rio interchange. These works will be completed in August, except for the Rio interchange which is estimated to be ready at the end of 2017.